SANTA MARIA DEL MAR
STATUS OF LEARNING CENTER AND RECTORY PROJECT
MAY 31, 2006Total Pledges Received ........................................................................... $1,661,000
Pledge Balance ........................................................................................$1,069,000
Cash Balance, including proceeds from sale of old rectory ...........................$ 905,000
less expenses incurred to dateTotal Estimated Cost ............................................................................ $2,280,000
[Not including covering the walkway between the church and Father O’Flaherty Hall
– estimated cost $370,000, which has been deferred at this time.]Summary
Total Construction Bid ......................................................................... $2,400,000
Fees, Permits, Furnishings, etc. ....................................$250,000........... $2,650,000
Less – Deferral of construction of covered walkway .....-$370,000
Total Estimated Cost .............................................................................$2,280,000Contractor – Bomar Construction, Inc., Ormond Beach, FL (lowest bidder)
Status of construction
All permits have been filed and construction should begin in the next few months when the permits have been issued. We will build the new parking lot first.FinancingIt is anticipated that the additional funds required will be raised by re-financing the existing church mortgage. The current balance is $1.4 million and the monthly payment of interest and amortization is $16,100. Re-financing, which will restore the mortgage to the original term of 15 years should not result in any appreciable increase in the monthly payment.Diocesan AssessmentThe Diocese has eliminated the tax on building funds. Effective July 1, 2006 no further tax will be paid on our pledge collections. This action will result in a savings of approximately $200,000. This saving is reflected in the above numbers.